Dhaka: The Rooppur Nuclear Power Plant has begun its second round of trial electricity supply to the national grid, marking another step towards commissioning the country’s first nuclear power facility.
The supply from the plant’s first unit started at 10:20am on Monday.
Dr Md Kabir Hossain, project director of the Rooppur Nuclear Power Plant construction project, said around 300 to 350 megawatts of electricity would be supplied to the national grid on a trial basis for 10 to 24 hours during this phase.
Various technical tests will be conducted during this period to assess the plant’s generation system and its integrated operation with the national grid, he added.
The plant first began trial electricity supply to the national grid on November 17 after a prolonged period of preparation, testing and technical assessments.
During the first phase, the plant’s first unit generated up to 375MW of electricity and supplied it to the national grid for around eight and a half hours. The estimated market value of the electricity supplied during that period was approximately Tk 2 crore. The grid connection was subsequently disconnected at 11:50pm.
Dr Md Zahedul Hasan, managing director of Nuclear Power Plant Company Bangladesh Limited (NPCBL), said the performance and stability of the turbine, generator and integrated operating system with the national grid had been closely monitored during the first grid connection (FGC).
As the test results were satisfactory, the plant was reconnected to the grid for the second phase after a necessary interval, he said.
He added that the grid connection would be disconnected again after several hours of monitoring, depending on the operational situation.
Considering the country’s electricity demand and supply challenges, the engineers, scientists and officials of NPCBL had worked tirelessly to make trial electricity supply to the national grid possible within the shortest possible time, he said.
Power generation would be increased or reduced as required during subsequent tests. The unit might also need to be temporarily shut down for certain technical assessments.
Power Grid Bangladesh PLC (PGB) would take the necessary measures to maintain the balance of the national grid in response to fluctuations in electricity generation, he added.
Praising the efforts of NPCBL officials and employees, the managing director said they were making every effort to supply electricity from the first unit to the national grid at full capacity before next summer, preferably between February and March 2027.
He expressed hope that the unit would then be able to supply around 1,150MW of electricity, significantly easing the country’s power shortage during the next summer.
Project officials said grid connection was an important technical milestone in establishing coordination between the power plant’s generation system and the national transmission network.
However, the beginning of trial electricity supply does not mean that the plant has entered full commercial operation, they clarified.
Generation capacity will be increased gradually in accordance with the guidelines of the International Atomic Energy Agency (IAEA) and international nuclear safety standards.
Following the completion of necessary tests and obtaining the required licences and regulatory approvals, the first unit is expected to gradually reach 100 per cent of its generation capacity.
Two units, each with a generation capacity of 1,200MW, are being built at the Rooppur Nuclear Power Plant. Once both units become operational, the facility will have a combined generation capacity of 2,400MW.
Following the first trial supply of electricity to the national grid, the second phase marks another significant milestone in Bangladesh’s journey towards nuclear power generation.