The first unit of the Rooppur Nuclear Power Plant in Pabna has started trial electricity generation, Science and Technology Minister Fakir Mahbub Anam confirmed to the media on Friday afternoon.
The development comes a day after the first unit received approval to begin the power start-up process from the Bangladesh Atomic Energy Regulatory Authority (BAERA) on Thursday (October 29).
At this stage, the reactor will achieve its first self-sustaining chain reaction through nuclear fission, allowing it to gradually produce energy in a stable and controlled manner.
All previous tests and examinations have been completed successfully, officials said.
According to guidelines of the International Atomic Energy Agency (IAEA), Stage B1 of the first unit of the Russian-assisted project has been completed largely successfully.
The complications involving the final test of the automatic pressure relief valves have also been resolved, paving the way for the next stage, known as B2.
During this phase, the nuclear reactor is prepared for initial operation before reaching criticality, the stage at which a self-sustaining nuclear chain reaction is established.
Following successful completion of the successive stages, the unit will gradually increase its output to 300 megawatts. Once it reaches that level, electricity will begin flowing commercially into the national transmission grid.