The seventh consignment of uranium fuel from Russia has arrived at the Rooppur Nuclear Power Plant in Ishwardi, Pabna, under tight security, completing the scheduled delivery of nuclear fuel for the plant’s second unit.
Three specialised trucks carrying the nuclear fuel entered the project premises at around 6:24am on Friday (November 20), under the supervision of the Bangladesh Army and other law enforcement agencies.
The consignment arrived at Hazrat Shahjalal International Airport in Dhaka on a special cargo flight from Russia on Thursday night. It was subsequently transported to Rooppur by road under strict security arrangements.
Police, intelligence agencies and other security personnel were deployed along the route to ensure safe transportation.
Traffic movement, particularly that of heavy vehicles, was temporarily restricted at several points to facilitate the convoy’s passage.
With the latest delivery, all seven scheduled consignments of nuclear fuel for the plant’s second unit have arrived.
A total of 163 uranium fuel assemblies are being supplied for the unit through seven cargo flights.
In addition, another 48 fuel assemblies for the first unit are scheduled to arrive in two further consignments to support future refuelling operations.
This will bring the total number of planned nuclear fuel shipments to nine.
The Rooppur Nuclear Power Plant, built with Russian technology and assistance from Russia’s state-owned nuclear corporation Rosatom, has two VVER-1200 reactor units, each with a generation capacity of 1,200 megawatts.
Once fully operational, the two units are expected to generate a combined 2,400MW of electricity for the national grid.
Meanwhile, the plant’s first unit has already begun trial electricity generation.
On November 17, it was connected to the national grid for the first time, supplying 350MW of electricity.
During the trial operation, the unit generated a maximum of 375MW over approximately eight and a half hours.
The first unit will undergo further technical tests and commissioning procedures before moving towards full-scale commercial operation.
Meanwhile, construction and commissioning work on the second unit is also progressing.