Govt approves Tk126cr for water, sewerage projects

Special Correspondent
26 November 2026 12:11 Updated: 26 November 2026 12:11

The government has approved two proposals involving a total expenditure of Tk126.35 crore to improve water supply in Khulna and sewerage services in Chattogram.

The approvals include Tk104.63 crore for constructing deep tube wells under the Khulna Water Supply Project (Phase II) and an additional Tk21.73 crore to extend the tenure and increase the contract value of technical consultancy services for Chattogram’s sewerage project.

The Cabinet Committee on Government Purchase approved the proposals at a meeting chaired by Finance Minister Amir Khosru Mahmud Chowdhury on Wednesday (November 25). The Finance Ministry disclosed the decisions on Thursday.

Under the Khulna project, RFL Plastics Ltd will construct deep tube wells and install pumps, motors, variable frequency drives, pump houses and electrical systems at a cost of Tk104.63 crore. The company will also be responsible for operating and maintaining the facilities for two years after construction.

Four bids were submitted in an international tender, but only RFL Plastics was found technically responsive. The project is jointly financed by the government and the Asian Development Bank (ADB).

For the Chattogram sewerage project, the committee approved an additional Tk21.73 crore for technical consultancy services, raising the consultants’ total contract value to Tk103.81 crore.

Four firms were jointly appointed as consultants in 2019: Malaysia’s Erinco Sdn Bhd and Bangladesh’s BETS Consulting Services Ltd, DevConsultants Ltd and the Institute of Water Modelling. Their original contract was worth Tk82.08 crore.

Advertisement

The consultancy contract expired on June 30. However, changes to the project design, revisions to the development project proposal and an extension of the project period have made continued consultancy services necessary, according to the proposal.

The revised contract will run until June 30, 2029, to support the remaining 24% of the project, including design-build contracts, contract management, quality control and construction supervision.