Govt approves 17 procurement proposals worth Tk 16,219cr

Staff Correspondent
26 November 2026 19:17 Updated: 26 November 2026 19:17

The government has approved 17 procurement proposals involving the import of fuel oil, fertiliser and wheat, railway development and various infrastructure projects. The approvals also include tariff rates for purchasing electricity from two power plants.

Excluding the two proposals for electricity purchases, the total estimated expenditure on the remaining 15 procurement proposals stands at around Tk 16,219.34 crore.

In addition, a variation proposal for a project of Chattogram WASA was approved, increasing the project cost by Tk 21.72 crore.

The approvals were given at a meeting of the Cabinet Committee on Government Purchase held at the Secretariat on Thursday (November 26), chaired by Finance Minister Amir Khosru Mahmud Chowdhury.

According to the Finance Ministry, the committee approved four proposals to import a total of 625,000 metric tonnes of fuel oil in three categories through international open tenders for the January-June period next year. The total cost will be Tk 8,010.13 crore.

Of the four proposals, Trafigura Pte Ltd emerged as the lowest bidder for three consignments. These include the import of 60,000 tonnes of gas oil (diesel) at $16.93 per barrel, costing Tk 960.40 crore, and 90,000 tonnes of gas oil at $17.45 per barrel, costing Tk 1,444.97 crore.

The company will also supply 350,000 tonnes of furnace oil at $69.82 per barrel at a cost of Tk 3,493.61 crore.

The remaining consignment of 125,000 tonnes of octane will be imported from Unipec Singapore Pte Ltd at $17.36 per barrel, costing Tk 2,111.14 crore.

Advertisement

The committee also approved three separate proposals to import a total of 110,000 tonnes of fertiliser.

Under a government-to-government (G2G) agreement, 40,000 tonnes of muriate of potash (MOP) fertiliser will be imported from the Canadian Commercial Corporation at $365.75 per tonne, costing Tk 182.65 crore.

In addition, 40,000 tonnes of bulk granular urea fertiliser will be purchased from Saudi Arabia’s SABIC Agri-Nutrients Company at $423.33 per tonne, while 30,000 tonnes of bagged granular urea will be procured from KAFCO at $397.87 per tonne.

The meeting also approved a proposal to import 440,000 tonnes of wheat from US Wheat Associates under a G2G arrangement. At $347.75 per tonne, the import will cost Tk 1,908.79 crore.

Two separate proposals to procure 10,000 tonnes each of sugar and lentils from the domestic market through tenders were also approved.

Meghna Sugar Refinery Ltd will supply sugar at Tk 104.95 per kg at a total cost of Tk 104.95 crore. Nabil Naba Foods Ltd will supply lentils at Tk 77.25 per kg, costing Tk 77.25 crore.

Two major procurement proposals for railway development were also approved. The projects involve converting the Chattogram-Dohazari metre-gauge railway line into a dual-gauge track.

Under package W-1, local company MAX Infrastructure Ltd will carry out the work at a cost of Tk 2,717.91 crore. Chinese company China Railway Group Ltd has been awarded package W-2 at a cost of Tk 1,911 crore.

The committee also approved tariff rates under two separate proposals for purchasing electricity from two power plants for 25 years.

The tariff for electricity from the 1,320MW Payra Ultra Super Critical Coal-Fired Power Plant, built by Bangladesh-China Power Company (Pvt) Ltd, has been set at 7.9858 US cents, equivalent to Tk 6.78, per kilowatt-hour. The total expenditure on electricity purchases from the plant over 25 years will amount to Tk 2,28,663 crore.

For the 1,320MW Maitree Super Thermal Power Plant in Rampal, built by Bangladesh-India Friendship Power Company (Pvt) Ltd, the tariff has been set at 8.2828 US cents, equivalent to Tk 9.11, per kilowatt-hour. The total cost of purchasing electricity from the plant over 25 years will be Tk 2,31,947 crore.

Meanwhile, the committee approved the appointment of contractors for two separate construction packages under the Khulna WASA Water Supply Project (Phase-II), being implemented with financing from the Asian Development Bank (ADB).

RFL Plastics Ltd will carry out one package at a cost of Tk 104.62 crore, while China First Metallurgical Group Company Ltd will implement the other at a cost of Tk 530.24 crore.

The committee also approved separate proposals to appoint contractors for improving the Karnaphuli Tunnel approach road at a cost of Tk 168 crore and reconstructing damaged roads, bridges and culverts in Sunamganj and Habiganj at a cost of Tk 148.88 crore.

Spectra Engineers Ltd has been awarded the Karnaphuli Tunnel approach road project, while Masud Hi-Tech Engineering Ltd will carry out the reconstruction work in Sunamganj and Habiganj.