Adani Godda unit restarts, power supply likely by noon

SB Desk
13 September 2026 15:16 Updated: 13 September 2026 15:16

Power supply to Bangladesh is expected to return to normal by noon on Sunday as a unit of Adani Power’s Godda plant in Jharkhand, India, has been restarted after a technical fault.

The second unit of the plant was successfully restarted at 5:17am Bangladesh time on Sunday, September 13, ahead of schedule. Synchronisation with the national grid is expected to be completed by 11:30am, paving the way for the resumption of power supply to Bangladesh before noon.

In a message on Sunday, Adani Power said the 800 MW unit of APL Godda had been brought back into operation ahead of schedule and was ready for synchronisation with the national grid.

The unit had been shut down late on September 11 after a technical fault was detected in its boiler. The shutdown sharply reduced generation at the plant and cut power supply to Bangladesh.

According to Power Grid Bangladesh data, the Godda plant had been generating more than 1,400 MW before the fault. Following the shutdown, supply fell below 750 MW, putting additional pressure on Bangladesh’s power system amid the ongoing fuel crisis and increasing load-shedding in several areas.

Bangladesh Power Development Board (BPDB) officials said repair work began immediately after the fault was identified. They had initially expected the unit to take at least 48 hours to restart, but the repair was completed ahead of schedule.

The Godda plant had also been operating below capacity since mid-August because of disruptions in coal transportation. Adani authorities attributed the disruption to railway congestion, restrictions on coal transport and heavy rainfall, which affected coal supplies to the plant.

Advertisement

As the situation improved towards the end of last month, generation gradually increased, reaching nearly 900 MW during the day and up to 1,200 MW in the evening. Generation later rose above 1,400 MW before the boiler fault forced one unit to shut down.

The Godda plant, one of Bangladesh’s major sources of imported electricity, has two units with a combined generation capacity of 1,600 MW.

Officials hope that the return of the faulty unit will boost electricity supply to the national grid and help ease load-shedding in the country.