Metro rail extension to Kamalapur set to open in July 2027

Staff Correspondent
22 November 2026 14:32 Updated: 22 November 2026 14:32

The extension of Dhaka’s metro rail from Motijheel to Kamalapur is progressing steadily, with regular passenger services on the 1.16-kilometre section now targeted to begin in July 2027 following several schedule revisions caused by construction delays.

According to sources concerned, the project is moving ahead with the construction of the station and installation of necessary infrastructure, including rail tracks and electrical and mechanical systems.

Data from Dhaka Mass Transit Company Limited (DMTCL) show that the currently operational section of MRT Line-6 stretches 20.10 kilometres. With the addition of the Kamalapur extension, the total route length will increase to 21.26 kilometres, serving 17 stations.

As of September 30, around 84.85 per cent of the civil construction work and 58 per cent of the electrical and mechanical work on the extended section had been completed.

The main physical infrastructure is scheduled for completion by December 31 this year. Construction of the viaduct has already been completed and handed over to the contractor for rail track installation.

The main structure of Kamalapur station has also been completed, while interior finishing, installation of electro-mechanical equipment and construction of entry and exit pathways are underway.

Architectural and related works are expected to be completed by December 31, 2026.

However, completing the physical infrastructure alone will not be enough to start passenger services. Rail tracks, power supply, automated signalling, automatic fare collection (AFC), platform safety systems and telecommunications facilities must be fully installed and commissioned.

Advertisement

Lifts and escalators will also need to be made operational before the launch.

After the installation of all systems, integrated testing and trial runs will be conducted to ensure operational safety and reliability. The outcome of these tests will determine the final date for launching passenger services.

The opening of the Motijheel-Kamalapur section was initially expected on January 1, 2027. The deadline was subsequently shifted to April-May 2027 before being revised again to July 2027.