Dhaka Airport’s Third Terminal to partially open on Dec 16

News Desk
14 November 2026 18:13 Updated: 14 November 2026 18:13

Partial view of third terminal: Photo colleted

After a prolonged wait, the third terminal of Hazrat Shahjalal International Airport is set to begin partial operations on December 16, initially handling two arriving and two departing flights.

The operations will be expanded gradually, with plans to bring the terminal into full service in phases.

Civil Aviation and Tourism Minister M Rashiduzzaman Millat has instructed all relevant agencies to complete the necessary preparations within the stipulated timeframe.

He gave the directive at a preparatory meeting on the inauguration and operation of the third terminal, held at the conference room of the Civil Aviation Authority of Bangladesh (CAAB) on Saturday.

The minister said partial operations could begin on December 16 if all preparations were completed as planned. Necessary work would then continue to facilitate the terminal’s full-scale operation in phases.

He described the opening of the third terminal at Hazrat Shahjalal International Airport as one of the major commitments of the current government.

“Prime Minister’s directive to begin operations within the stipulated timeframe must be given the highest priority. Every relevant agency must properly fulfil its responsibilities and complete all necessary work on time,” he said.

The meeting reviewed various aspects of the preparations, including the operation of immigration booths, installation of baggage belts and necessary scanners, trial operations and the signing of relevant agreements.

Advertisement

Representatives of the agencies concerned assessed progress and discussed the remaining tasks that need to be completed without delay.

The meeting also discussed coordination among different stakeholders, the division of responsibilities and other measures required to launch the terminal’s operations smoothly.

Among those present were Invest Bangladesh Chairman Chowdhury Ashik Mahmud Bin Harun, Dhaka-18 MP SM Jahangir Hossain, Prime Minister’s Special Assistant for Civil Aviation and Tourism Gias Uddin, Civil Aviation and Tourism Secretary Dr Nurunnahar Chowdhury and National Board of Revenue Chairman Ahsan Habib.

Representatives of CAAB, the Ministry of Civil Aviation and Tourism, and the Japanese consortium involved in the construction of the third terminal also attended the meeting.