The third terminal of Hazrat Shahjalal International Airport will be inaugurated on December 16, but it will take another 14 months to become fully operational. Initially, the terminal will begin partial operations with four flights, with the first flight to be operated by Biman Bangladesh Airlines.
Civil Aviation and Tourism Minister M Rashiduzzaman Millat disclosed the information while speaking to journalists at the Secretariat on Monday afternoon.
The minister said preparations for the inauguration were underway and an agreement with the Japanese consortium would be finalised by November 30. The terminal would begin partial operations with four flights on December 16.
He said Biman Bangladesh Airlines would operate the first flight on the inauguration day. However, full-scale operations would take another 14 months.
Regarding the inauguration of Cox’s Bazar Airport as an international airport, the minister said it would be inaugurated once the prime minister fixed a date.
The long-awaited third terminal was built with financing of Tk 21,139 crore from the Japan International Cooperation Agency (JICA).
Earlier, a Biman Bangladesh Airlines flight used the terminal on a trial basis in August. However, commercial operations could not begin due to a lack of agreement with the Japanese consortium.
The consortium, led by Sumitomo Corporation, includes Japan Airport Terminal Co, Narita International Airport Corporation, Sojitz Corporation and Japanese government agencies. It had been promised an agreement to operate the terminal under a public-private partnership (PPP) model.
The agreement was part of the JICA-funded project initiated during the previous Awami League government. However, after the interim government took office, Biman Bangladesh Airlines was assigned ground-handling responsibilities at the new terminal for two years, triggering dissatisfaction among the consortium members.
The terminal was formally inaugurated through a soft opening in October 2023. It is expected to increase the airport’s annual passenger-handling capacity from eight million to 24 million and significantly expand cargo-handling capacity.
The facility is connected to the Dhaka Metro Rail, Elevated Expressway and Hajj Camp, and is expected to become a major hub for the country’s aviation sector.
Construction of the third terminal began in December 2019. Built over an area of 542,000 square metres, the terminal has a floor space of 230,000 square metres.
The modern facility will feature 26 boarding bridges, 115 check-in counters, 66 departure immigration desks, 59 arrival immigration desks and three VIP immigration desks.