Real estate firms forge RAJUK seals to fake approvals: TIB

25 November 2026 15:30 Updated: 25 November 2026 15:30

Several real estate companies in Bangladesh are developing housing projects and selling plots without proper approvals or clearances, while some are allegedly forging approval documents and layout plans using counterfeit seals and letterheads of the Rajdhani Unnayan Kartripakkha (RAJUK), according to a Transparency International Bangladesh (TIB) study.

The findings were presented on Wednesday at TIB’s Dhaka office in a study titled Governance Challenges in Land Development in the Private Housing Sector in Dhaka City.

The study found that some developers use expired, backdated or irregularly obtained approvals to implement residential projects. They also allegedly mislead customers by presenting company registration numbers as project registration numbers.

According to the research, some companies fail to provide promised community facilities, including playgrounds, schools, places of worship and other public amenities. In some cases, land designated for such facilities is reportedly sold later.

Developers also allegedly divide large projects into smaller sections to avoid legal obligations and responsibilities for providing community facilities. Some collect additional charges from plot buyers for facilities that are supposed to be provided free of cost.

The study further found that some companies expand projects beyond approved boundaries by filling wetlands and low-lying areas, in violation of environmental conditions and planning regulations.

Advertisement

It cited an example from the Holan and Ashkona areas of Dhaka, where a company allegedly expanded a project beyond its approved 43 acres by filling around 230 acres of unauthorised wetlands and low-lying land. The High Court later declared the expansion illegal.

Other irregularities include unauthorised changes to approved layouts, land use and infrastructure, as well as inadequate safety measures for construction workers and poor dust and noise control at construction sites.

TIB also identified alleged land-related fraud, including forged registration numbers and deeds, false project approval claims, and selling plots before completing land acquisition. Some companies reportedly use signboards on privately owned or leased land to portray it as part of their projects.

The research also found allegations of selling the same plot to multiple buyers, changing previously allocated plots to favour influential customers and assigning ordinary buyers less valuable plots.

Buyers also face problems with ownership transfers, arbitrary cancellation of allocations, delays in refunding payments and alleged misappropriation of money.

Some developers reportedly delay issuing receipts for instalments, fail to adjust previous payments and subsequently label buyers as defaulters to impose penalties. Heirs of deceased buyers also face administrative complications and financial harassment when transferring contracts.

Presenting the findings, TIB Executive Director Dr Iftekharuzzaman said it was virtually impossible to identify real estate companies entirely free from irregularities.

He said allegations of abuse of power, corruption and legal violations existed across almost the entire sector, although the extent varied from company to company.