The first unit of the Rooppur Nuclear Power Plant in Pabna has entered the final testing phase ahead of electricity generation, following approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) on Thursday afternoon.
The phase, known as “power start” or “C-stage”, will assess the performance of the reactor, cooling systems, turbine, generator and control systems. The reactor’s power level will be gradually increased to verify that all systems operate safely and stably.
Mohammad Zahedul Hassan, managing director of Nuclear Power Plant Company Bangladesh Limited (NPCBL), said testing would initially begin at zero power. Once the plant reaches 30 per cent of its capacity, it will start supplying electricity to the national grid on a trial basis.
The plant could initially supply around 300 megawatts of electricity to the grid, with trial supply expected to begin in December.
The start of the reactor’s nuclear reaction was previously delayed after defects were detected during safety valve tests. Following the completion of the necessary tests and regulatory approval, the first unit began its nuclear reaction on October 11.
Russian contractor Atomstroyexport is constructing two units at the Rooppur plant, each with a capacity of 1,200 megawatts. The total project cost has been estimated at Tk 138,686 crore.
Officials expect trial operations to continue for seven to eight months after electricity generation begins.