The ninth and final consignment of uranium fuel for the Rooppur Nuclear Power Plant has arrived at the project site in Ishwardi, Pabna, completing the scheduled delivery of nuclear fuel from Russia.

The latest shipment marks the completion of nine consignments planned to supply additional nuclear fuel for the plant’s two reactor units.

According to the original delivery plan announced by Russia’s state nuclear energy corporation Rosatom, 163 uranium fuel assemblies were scheduled to be delivered in seven consignments for Unit 2, while another 48 assemblies were allocated for refuelling Unit 1 through two consignments.

The shipments were transported from Russia by special cargo aircraft and subsequently carried to the Rooppur project site in specially equipped vehicles under tight security arrangements.

The Bangladesh Army, police and other law enforcement agencies were involved in ensuring the safe transportation of the nuclear fuel.

The Rooppur Nuclear Power Plant, built with Russian technical and financial assistance, has two VVER-1200 reactor units, each with a generation capacity of 1,200 megawatts (MW).

Once fully operational, the plant is expected to generate a combined 2,400MW of electricity.

Meanwhile, Unit 1 began supplying electricity to the national grid on a trial basis on November 17, generating up to 375MW during its initial grid connection.

The completion of the uranium deliveries marks an important milestone in the commissioning and operational preparations of Bangladesh’s first nuclear power plant.

Advertisement

Background: The eighth consignment arrived at the project site on November 24, according to reports.

Headline alternative: Final Uranium Shipment Reaches Rooppur, Completing Nine-Consignment Delivery